MCC Board rejects speculative schedule for transmission line project

KATHMANDU, Dec 4: The Board of Directors meeting of the Millennium Challenge Account Nepal (MCA) has directed a reassessment of the proposed timeline for the procurement and construction of the transmission line project.

सम्बन्धित सामग्री

Tower construction process begins in Tanahun under MCC project

The work of 199 towers and one substation is being advanced in Tanahun for the power transmission line project under the Millennium Challenge Corporation (MCC). According to the District Liaison Office of

MCC board rejects speculative schedule for transmission line project

KATHMANDU, Dec 4: The Board of Directors meeting of the Millennium Challenge Account Nepal (MCA) has directed a reassessment of the proposed timeline for the procurement and construction of the transmission line project.

MCA-Nepal scraps MCC transmission line contracts due to high cost bids

KATHMANDU, Oct 13: All the contracts for the transmission line project by the Millennium Challenge Corporation (MCC) have been canceled. The Millennium Challenge Account (MCA) Nepal issued a notice on Friday, stating that all these contracts were canceled.

MCA-Nepal scraps MCC transmission line contracts due to high cost bids

KATHMANDU, Oct 13: All the contracts for the transmission line project by the Millennium Challenge Corporation (MCC) have been canceled. The Millennium Challenge Account (MCA) Nepal issued a notice on Friday, stating that all these contracts were canceled.

Land acquisition process for transmission line project

The process has begun for acquiring land for the construction of the 400 kV transmission line being operated under the Millennium Challenge Corporation (MCC) compact.

Land acquisition process for transmission line project

The process has begun for acquiring land for the construction of the 400 kV transmission line being operated under the Millennium Challenge Corporation (MCC) compact.