Narayangadh-Butwal road expansion: 23% of work done in 48 months
The widening of the Narayangadh-Butwal road section along the East-West Highway has so far made only 23 per cent progress.
The post Narayangadh-Butwal road expansion: 23% of work done in 48 months appeared first on OnlineKhabar English News.
Kathmandu, November 14 — Prime Minister KP Sharma Oli has stated that a decision will be reached soon regarding the delay in the construction of the Narayangadh–Butwal road section under the East-West Highway.
During a discussion at the Prime Minister's residence in Baluwatar today, which included concerned ministers, ministry officials, and representatives from Rupandehi, Nawalparasi (Bardaghat Susta West), and Nawalparasi (Bardaghat Susta East), Prime Minister Oli emphasized that if construction does not begin by December 2024, there will be no option but to terminate the contract.
He stated that if the contractor company performs reliably, it would...
Kathmandu, November 14 — Prime Minister KP Sharma Oli has stated that a decision will be reached soon regarding the delay in the construction of the Narayangadh–Butwal road section under the East-West Highway.
During a discussion at the Prime Minister's residence in Baluwatar today, which included concerned ministers, ministry officials, and representatives from Rupandehi, Nawalparasi (Bardaghat Susta West), and Nawalparasi (Bardaghat Susta East), Prime Minister Oli emphasized that if construction does not begin by December 2024, there will be no option but to terminate the contract.
He stated that if the contractor company performs reliably, it would...
NAWALPUR: The ongoing expansion of the Narayangadh-Butwal road section has come to a standstill due to relentless rainfall. Ashish Thapa Magar, the project chief overseeing the eastern section of the Narayangadh-Butwal Road Expansion Project, explained that efforts are now focused on ensuring smooth traffic flow rather than widening the road. “We are prioritizing measures to […]