Kathmandu. Preparations are underway to bring the Krishna Bhir road section, which was obstructed due to a landslide caused by the flood in the Trishuli River, into operation for traffic within three days. According to Sajana Adhikari, the plan chief of the Nagdhunga-Mugling Road Project (West Section), the work of constructing a new track from the mountainside of the collapsed road has been completed. Currently, the work of preparing the subgrade by grading down the new track is underway. Adhikari informed that the work has been expedited by mobilizing the necessary equipment and construction teams for road construction. She stated...