Tanahu. The under-construction Tanahu Hydropower Project with a capacity of 140 megawatts has achieved 75 percent progress so far. The project, being built in Jhuptar of Rishing Rural Municipality-1, has reported 75 percent progress in work across all three 'packages', the project stated. Project Chief Shyamji Bhandari informed that work is underway on Package 1, which includes the dam and related structures (headworks), Package 2, which includes the main tunnel, powerhouse, and related equipment, and Package 3, which includes the Damuali-Bharatpur 220 KV transmission line. The work for Package 1, including the dam and related structures, is being carried out...