Progress of Expressway construction made public

The Nepali Army has made public the progress details of the Kathmandu-Terai/ Madhesh Expressway project claiming that it has gained financial progress of 97.34 per cent. The Nepali Army, which has been given the responsibility of construction management by the government, has made public the progress details of the project till the end of the Fiscal Year 2020/21. As per the progress details issued by the Directorate of Public Relations and Information of the Army Headquarters Tuesday evening, the annual financial progress of the project stands at 97.34 per cent out of the total budget allocation of Rs. 8.96 billion.