Kathmandu. About 90 percent construction work has been completed on the Krishnabhir section of the Prithvi Highway.Cutting, gravelling, and sub-surface drainage construction have been completed on the 270-meter newly constructed Krishnabhir road section, informed the Road Division Office, Bharatpur. The office has provided information through social media that the remaining sub-base work is being carried out to be completed by Wednesday evening. Floodlights have been arranged for construction work even during the night.With the construction work reaching its final stage, all types of vehicles will be operated in both directions at Krishnabhir from October 1, the office has stated....